The U.S. Army Corps of Engineers began geotechnical investigations supporting a proposed four-foot deepening of Port Tampa Bay’s federal navigation channel.

The work involves drilling soil borings and collecting subsurface samples at multiple locations. Results will inform engineering and design decisions for the Tampa Harbor Navigation Improvement Project, which would deepen the main channel from 43 to 47 feet. The main channel extends about 42 miles.

Fieldwork is expected to continue through the end of 2026.

Port Tampa Bay said the additional depth would allow vessels to carry more cargo per call, potentially reducing transportation costs and the number of vessel calls required to move a given volume. The port handles fuel, construction materials, steel, automobiles, consumer products and other cargoes.

The Army Corps’ General Reevaluation Report estimated that routing cargo through Tampa instead of another Southeastern port and then trucking it to the region could eliminate more than 17 million truck miles annually. Using the study’s 2024 assumptions, the change could avoid about 26,000 tonnes of carbon dioxide emissions and reduce nationwide transportation costs by about $90 million annually.

The project is expected to generate more than 21 million cubic yards of dredged material. Proposed beneficial uses include beach and dune restoration, island stabilization and habitat creation.

Plans include using material to help restore Egmont Key, a barrier island at the entrance to Tampa Bay, and restoring about 55 acres of deep-water area near the Sunshine Skyway Bridge as shallow-water habitat.

The design incorporates a channel-within-a-channel approach that would deepen the center of the existing channel while limiting expansion of its overall footprint.

Congress authorized the navigation project in 2024. Port Tampa Bay describes it as the largest infrastructure initiative in the port’s history, although the release did not provide a construction schedule, total cost or funding status.

U.S. Army Corps of Engineers personnel collect subsurface soil samples as part of the channel deepening project’s geotechnical investigation. PHOTO: Port Tampa Bay